What's Happening to the Station! UPDATED May 28th

Tangent Rural Fire District received a grant to retrofit the fire station to current earthquake standards. This work will continue through till the month of June, 2020.

UPDATE!  All aspects of the seismic upgrade are completed, from the shoring of the walls to the anchoring straps into the foundation. Karen has returned to her office. The remainder of the work will focus on a new coat of paint for the station and new bay doors for the apparatus bays. The total completion is still looking to occur in June. And the project still appears to be completed well within the original grant amount..