What's Happening to the Station! UPDATE!!

Tangent Rural Fire District recently received a grant to retrofit the fire station to current earthquake standards. This work will continue through till the summer of 2020.

UPDATE! Most of the structual and foundation work is being completed. Holes are being filled with concrete, flooring is being ordered and sheetrock and painting is wrapping up. Our office administartor, Karen Duckworth has been working out of a makeshift office and is ready to return to her regular office, hopefully in late April. The remainder of the work will focus on the station's two roofs and the final leg of the project is the station gets a new coat of paint. The total completion looking to occur early June. The Good News is the project appears to be coming well under the amount recieved from grant money, in which no dollars the District's fund will have to be used.